A new plant in Mer (France)

  • 2008: launch of the studies on the project of new plant
  • 2011: selection IDEC proposal and the validation of the project
  • 2012: obtaining of the building permit
  • 2013 (March): ICPE authorization
  • 2013 (September): launch of the building process

Entirely thought around the flow management, this new plant should allow us to reach an important optimization of our productivity. If the investment is significant for the group, it demonstrates our commitment to our customers and our employees as well as our confidence and that of our partners in the relevance of our strategic choices and our capacity of evolution.

 